Terms Used In Louisiana Revised Statutes 38:2246

  • Claimant: as used in this Chapter , means any person to whom money is due pursuant to a contract with the owner or a contractor or subcontractor for doing work, performing labor, or furnishing materials or supplies for the construction, alteration, or repair of any public works, or for transporting and delivering such materials or supplies to the site of the job by a for-hire carrier, or for furnishing oil, gas, electricity, or other materials or supplies for use in machines used in the construction, alteration, or repair of any public works, including persons to whom money is due for the lease or rental of movable property used at the site of the immovable and leased to the owner, contractor, or subcontractor by written contract, and including registered or certified surveyors or engineers or consulting engineers, or licensed architects, or their professional subconsultants employed by the owner or by the contractor or subcontractor in connection with the building of any public work. See Louisiana Revised Statutes 38:2242
  • Trial: A hearing that takes place when the defendant pleads "not guilty" and witnesses are required to come to court to give evidence.

A.  After amicable demand for payment has been made on the principal and surety and thirty days have elapsed without payment being made, any claimant recovering the full amount of his timely and properly recorded or sworn claim, whether by concursus proceeding or separate suit, shall be allowed ten percent attorney’s fees which shall be taxed in the judgment on the amount recovered.  

B.  If the trial court finds that such an action was brought by any claimant without just cause or in bad faith, the trial judge shall award the principal or surety a reasonable amount as attorney’s fees for defending such action.  

Acts 1991, No. 543, §1.