Michigan Laws 324.30304b – Issuance of state programmatic general permits; agreement with United States army corps of engineers; applicability of subsections (2) and (3)
Current as of: 2024 | Check for updates
|
Other versions
Terms Used In Michigan Laws 324.30304b
- Department: means the department of environmental quality. See Michigan Laws 324.30301
- in writing: shall be construed to include printing, engraving, and lithographing; except that if the written signature of a person is required by law, the signature shall be the proper handwriting of the person or, if the person is unable to write, the person's proper mark, which may be, unless otherwise expressly prohibited by law, a clear and classifiable fingerprint of the person made with ink or another substance. See Michigan Laws 8.3q
- Jurisdiction: (1) The legal authority of a court to hear and decide a case. Concurrent jurisdiction exists when two courts have simultaneous responsibility for the same case. (2) The geographic area over which the court has authority to decide cases.
- Rare and imperiled wetland: means any of the following:
(i) Great Lakes marsh. See Michigan Laws 324.30301state: when applied to the different parts of the United States, shall be construed to extend to and include the District of Columbia and the several territories belonging to the United States; and the words "United States" shall be construed to include the district and territories. See Michigan Laws 8.3o United States: shall be construed to include the district and territories. See Michigan Laws 8.3o Wetland: means a land or water feature, commonly referred to as a bog, swamp, or marsh, inundated or saturated by water at a frequency and duration sufficient to support, and that under normal circumstances does support, hydric soils and a predominance of wetland vegetation or aquatic life. See Michigan Laws 324.30301
(1) The department shall pursue an agreement with the United States army corps of engineers for the corps to issue state programmatic general permits under section 404(e) of title IV of the federal water pollution control act, 33 USC 1344, for activities regulated under this part in waters over which the corps retains jurisdiction under section 404(g)(1) of title IV of the federal water pollution control act, 33 USC 1344.
(2) This subsection applies beginning January 1, 2011. This subsection applies to an application for a permit under this part only if the application is for an activity or use in waters over which the corps retains jurisdiction under section 404(g)(1) of title IV of the federal water pollution control act, 33 USC 1344, and if the corps has not issued a state programmatic general permit for the activity or use. In such a case, if requested by the applicant in the application, all of the following apply:
(a) The department shall approve or deny the application for a permit under this part not more than 30 days after the corps grants or denies an application for a permit for the project under section 404(a) of title IV of the federal water pollution control act, 33 USC 1344, or by the end of the processing period otherwise provided for in section 1301, whichever is later. If a project proposed in a permit application processed under this subsection also requires authorization under 1 or more of parts 31, 301, 315, 323, 325, or 353, the requirements of this subdivision also apply to the department’s decision under that part or parts.
(b) Subject to subsection (3), if the corps grants a permit for the project, the department shall grant a permit under this part without conditions or limitations other than those imposed by the corps unless any of the following apply:
(i) The wetland is a rare and imperiled wetland.
(ii) The wetland is regionally significant for the protection of fisheries, wildlife, or migratory birds.
(iii) The site is described in section 30309(a), (e), or (g).
(iv) The proposed project involves a use or activity not regulated under section 404(a) of title IV of the federal water pollution control act, 33 USC 1344.
(3) The department shall inform the applicant in writing of the basis for a finding that the requirements of subsection (2)(b)(i), (ii), (iii), or (iv) are met and the specific reasons why denial of the permit or the imposition of additional conditions or limitations on the permit is consistent with this part and rules promulgated under this part.
(4) Subsections (2)(b) and (3) apply only to the department’s decision under this part notwithstanding that the project proposed in the application also requires authorization under 1 or more of parts 31, 301, 315, 323, 325, and 353.