1.  If a public body and a contractor enter into a contract for a public work, the contractor may withhold as retainage not more than 5 percent from the amount of any progress payment due under a subcontract which is made before 50 percent of the work has been completed under the subcontract.

Ask a legal question, get an answer ASAP!
Click here to chat with a lawyer about your rights.

Terms Used In Nevada Revised Statutes 338.555

  • Contract: A legal written agreement that becomes binding when signed.
  • Contract: means a written contract entered into between a contractor and a public body for the provision of labor, materials, equipment or supplies for a public work. See Nevada Revised Statutes 338.010
  • Contractor: means :

    (a) A person who is licensed pursuant to the provisions of chapter 624 of NRS. See Nevada Revised Statutes 338.010

  • Public body: means the State, county, city, town, school district or any public agency of this State or its political subdivisions sponsoring or financing a public work. See Nevada Revised Statutes 338.010
  • Public work: means any project for the new construction, repair or reconstruction of a project financed in whole or in part from public money for:

    (a) Public buildings;

    (b) Jails and prisons;

    (c) Public roads;

    (d) Public highways;

    (e) Public streets and alleys;

    (f) Public utilities;

    (g) Publicly owned water mains and sewers;

    (h) Public parks and playgrounds;

    (i) Public convention facilities which are financed at least in part with public money; and

    (j) All other publicly owned works and property. See Nevada Revised Statutes 338.010

  • Subcontract: means a written contract entered into between:

    (a) A contractor and a subcontractor or supplier; or

    (b) A subcontractor and another subcontractor or supplier, for the provision of labor, materials, equipment or supplies for a construction project. See Nevada Revised Statutes 338.010

  • Subcontractor: means a person who:

    (a) Is licensed pursuant to the provisions of chapter 624 of NRS or performs such work that the person is not required to be licensed pursuant to chapter 624 of NRS; and

    (b) Contracts with a contractor, another subcontractor or a supplier to provide labor, materials or services for a construction project. See Nevada Revised Statutes 338.010

  • Supplier: means a person who provides materials, equipment or supplies for a construction project. See Nevada Revised Statutes 338.010

2.  After 50 percent of the work required by the contract has been performed, the contractor shall pay any additional progress payments due under the subcontract without withholding any additional retainage if, in the opinion of the contractor, satisfactory progress is being made in the work under the subcontract, and the payment must be equal to that paid by the public body to the contractor for the work performed by the subcontractor. If the contractor continues to withhold retainage from remaining progress payments:

(a) If the contractor does not withhold any amount pursuant to NRS 338.560:

(1) The contractor may not withhold more than 2.5 percent of the amount of any progress payment; and

(2) Before withholding any amount pursuant to subparagraph (1), the contractor must pay to the subcontractor 50 percent of the amount of any retainage that was withheld from progress payments pursuant to subsection 1; or

(b) If the contractor withholds any amount pursuant to NRS 338.560:

(1) The contractor may not withhold more than 5 percent of the amount of any progress payment; and

(2) The contractor may continue to retain the amount of any retainage that was withheld from progress payments pursuant to subsection 1.

3.  If the contractor receives a payment of interest earned on the retainage or an amount withheld from a progress payment, the contractor shall, within 10 days after he or she receives the money, pay to each subcontractor or supplier that portion of the interest received from the public body which is attributable to the retainage or amount withheld from a progress payment by the contractor to the subcontractor or supplier.

4.  If, pursuant to subsection 3 of NRS 338.515, the public body pays to the contractor an amount of any retainage that was withheld from progress payments pursuant to subsection 1 of NRS 338.515 for the portion of the work which has been performed by the subcontractor, the contractor must pay to the subcontractor the portion of any retainage withheld by the contractor pursuant to this section for the portion of the work.