New Jersey Statutes 40:55D-134. Extension of project exemption
Terms Used In New Jersey Statutes 40:55D-134
- Appeal: A request made after a trial, asking another court (usually the court of appeals) to decide whether the trial was conducted properly. To make such a request is "to appeal" or "to take an appeal." One who appeals is called the appellant.
- person: includes corporations, companies, associations, societies, firms, partnerships and joint stock companies as well as individuals, unless restricted by the context to an individual as distinguished from a corporate entity or specifically restricted to one or some of the above enumerated synonyms and, when used to designate the owner of property which may be the subject of an offense, includes this State, the United States, any other State of the United States as defined infra and any foreign country or government lawfully owning or possessing property within this State. See New Jersey Statutes 1:1-2
(2) This act shall automatically extend any project exemption granted pursuant to subsection d. of section 4 of P.L.1987, c.156 (C. 13:9B-4) from the requirements of section 16 of P.L.1987, c.156 to maintain a transition area adjacent to freshwater wetlands, if the freshwater wetlands which would be affected by the project are not freshwater wetlands of exceptional resource value.
b. Any person who may be eligible for an automatic extension pursuant to the provisions of subsection a. of this section may submit an application to the Department of Environmental Protection and Energy for a determination of whether the freshwater wetlands affected by the project are freshwater wetlands of exceptional resource value as defined by the Department of Environmental Protection and Energy pursuant to P.L.1987, c.156 and any rules and regulations adopted pursuant thereto. This application shall be limited to a description of the location of the project by lot and block number and a delineation of the wetlands affected by the project. If the Department of Environmental Protection and Energy does not make a determination requested pursuant to this subsection within 90 days of receipt of the application therefor, the freshwater wetlands shall be deemed to not be of exceptional resource value. The Office of Administrative Law shall provide for expedited appeal by the applicant of any determination that the freshwater wetlands affected by a project potentially eligible for an automatic extension pursuant to the provisions of subsection a. of this section are classified as freshwater wetlands of exceptional resource value.
c. In the event the Department of Environmental Protection and Energy obtains additional information clearly and convincingly demonstrating that a freshwater wetlands previously determined by the Department of Environmental Protection and Energy or otherwise deemed to not be of exceptional resource value are actually freshwater wetlands of exceptional resource value, the Department of Environmental Protection and Energy may, within one year after the date of its original determination or the date on which the freshwater wetlands were deemed not to be of exceptional resource value, reclassify the freshwater wetlands as a freshwater wetlands of exceptional resource value, and require compliance with the requirements of section 16 of P.L.1987, c.156 to maintain a transition area adjacent to freshwater wetlands. This subsection shall not apply to any project the actual construction of which has commenced at the time the Department of Environmental Protection and Energy provides notice to the applicant that the previous wetlands resource classification may be modified.
L.1992,c.82,s.5.