New Jersey Statutes 58:10C-27.1. Extensions permitted; application
Terms Used In New Jersey Statutes 58:10C-27.1
- Oversight: Committee review of the activities of a Federal agency or program.
- person: includes corporations, companies, associations, societies, firms, partnerships and joint stock companies as well as individuals, unless restricted by the context to an individual as distinguished from a corporate entity or specifically restricted to one or some of the above enumerated synonyms and, when used to designate the owner of property which may be the subject of an offense, includes this State, the United States, any other State of the United States as defined infra and any foreign country or government lawfully owning or possessing property within this State. See New Jersey Statutes 1:1-2
- State: extends to and includes any State, territory or possession of the United States, the District of Columbia and the Canal Zone. See New Jersey Statutes 1:1-2
(1) a licensed site remediation professional has been retained to conduct a remediation of the site;
(2) any remediation requirements included in mandatory remediation timeframes adopted pursuant to section 28 of P.L.2009, c.60 (C. 58:10C-28), for the site have been met at the time of the certification;
(3) technically complete submissions have been made in compliance with all rules and regulations for site remediation, as applicable, for the (a) initial receptor evaluation, (b) immediate environmental concern source control report, (c) light non-aqueous phase liquid interim remedial measure report, (d) preliminary assessment report, and (e) site investigation report;
(4) a remediation funding source has been established, if required of the applicant by section 25 of P.L.1993, c.139 (C. 58:10B-3);
(5) if a remediation funding source is not required to be established by the applicant pursuant to law, then a remediation trust fund for the estimated cost of the remedial investigation has been established pursuant to the standards established in section 25 of P.L.1993, c.139 (C. 58:10B-3);
(6) any oversight costs imposed by the department, known at the time of the application, and not in dispute on the date of enactment of P.L.2013, c.283 (C. 58:10C-27.1 et al.), have been paid to the department; and
(7) the annual fees imposed by the department for the remediation and remediation funding source surcharges imposed pursuant to section 33 of P.L.1993, c.39 (C. 58:10B-11) have been paid to the department, as applicable.
An application pursuant to this subsection shall be submitted to the department by March 7, 2014 or 30 days after the date of enactment of P.L.2013, c.283 (C. 58:10C-27.1 et al.), whichever is later.
b. For any site subject to the provisions of paragraph (3) of subsection a. of section 27 of P.L.2009, c.60 (C. 58:10C-27), if the failure to complete the remedial investigation of the contaminated site is due to a delay in the provision of State financial assistance for the remediation from the Hazardous Discharge Site Remediation Fund, upon application by a person responsible for conducting the remediation, an extension of time shall be provided to allow for the completion of the remedial investigation prior to the department taking direct oversight, except as provided in subsection c. of this section. The applicant shall submit to the department a certification that the person responsible for conducting the remediation filed a technically and administratively complete application for funding prior to March 7, 2014 or 30 days after the date of enactment of P.L.2013, c.283 (C. 58:10C-27.1 et al.), whichever is later, qualifies for funding, and remains eligible for funding. Every six months after the submission of the application for the extension of time pursuant to this subsection, the applicant shall submit to the department a certification with an update on the status of the funding application.
The extension of time for the completion of a remedial investigation of a contaminated site prior to the department taking direct oversight of the remediation pursuant to this subsection shall be no more than two years after receipt of funding, or no more than two years after the applicant is no longer eligible for funding.
An application for an extension of time pursuant to this subsection shall be submitted to the department by March 7, 2014 or 30 days after the date of enactment of P.L.2013, c.283 (C. 58:10C-27.1 et al.), whichever is later.
c. An application submitted pursuant to subsection a. or b. of this section shall be deemed approved upon receipt by the department. The department may undertake direct oversight of a remediation if, at any time during the extension of time: (1) the conditions imposed pursuant to subsection a. or b. of this section, as the case may be, are no longer met; or (2) the person responsible for conducting the remediation fails to meet a mandatory remediation timeframe after submission of the certification submitted pursuant to this section. The department shall so notify the person responsible for conducting the remediation, in writing, that the extension of time for completion of the remedial investigation is revoked because of the applicant’s failure to continue to comply with the conditions required, or the applicant’s failure to submit one or more of the certifications required pursuant to subsection a. or b. of this section, or that the information included in a certification is incomplete, incorrect, false, or otherwise deficient.
d. The department shall provide notice on its internet website of any extensions provided pursuant to this section. In the notice, the department shall provide the name and location of the site for which the extension is provided and the length of the extension of time.
L.2013, c.283, s.1.