A. Any person, firm or corporation or any other entity desiring to appropriate for beneficial use any of the waters described in N.M. Stat. Ann. Chapter 72, Article 12 shall apply to the state engineer in a form prescribed by the state engineer. In the application, the applicant shall designate:

Ask a legal question, get an answer ASAP!
Click here to chat with a lawyer about your rights.

Terms Used In New Mexico Statutes 72-12-3

  • Appropriation: The provision of funds, through an annual appropriations act or a permanent law, for federal agencies to make payments out of the Treasury for specified purposes. The formal federal spending process consists of two sequential steps: authorization
  • Corporation: A legal entity owned by the holders of shares of stock that have been issued, and that can own, receive, and transfer property, and carry on business in its own name.

(1)     the particular underground stream, channel, artesian basin, reservoir or lake from which water will be appropriated;

(2)     the beneficial use to which the water will be applied; (3)     the location of the proposed well;

(4)     the name of the owner of the land on which the well will be located; (5)     the amount of water applied for;

(6)     the place of the use for which the water is desired; and

(7)     if the use is for irrigation, the description of the land to be irrigated and the name of the owner of the land.

B. If the well will be located on privately owned land and the applicant is not the owner of the land or the owner or the lessee of the mineral or oil and gas rights under the land, the application shall be accompanied by an acknowledged statement executed by the owner of the land that the applicant is granted access across the owner’s land to the drilling site and has permission to occupy such portion of the owner’s land as is necessary to drill and operate the well. This subsection does not apply to the state or any of its political subdivisions. If the application is approved, the applicant shall have the permit and statement, executed by the owner of the land, recorded in the office of the county clerk of the county in which the land is located.

C. No application shall be accepted by the state engineer unless it is accompanied by all the information required by Subsections A and B of this section.

D. Upon the filing of an application, the state engineer shall proceed in accordance with the provisions of Section 1 [72-2-20 NMSA1978] of this 2019 act regarding notice of the application. Any person, firm or corporation or other entity objecting that the granting of the application will impair the objector’s water right shall have standing to file objections or protests. Any person, firm or corporation or other entity objecting that the granting of the application will be contrary to the conservation of water within the state or detrimental to the public welfare of the state and showing that the objector will be substantially and specifically affected by the granting of the application shall have standing to file objections or protests; provided, however, that the state or any of its branches, agencies, departments, boards, instrumentalities or institutions, and all political subdivisions of the state and their agencies, instrumentalities and institutions shall have standing to file objections or protests.

E. After the expiration of the time for filing objections, if no objections have been filed, the state engineer shall, if the state engineer finds that there are in the underground stream, channel, artesian basin, reservoir or lake unappropriated waters and that the proposed appropriation would not impair existing water rights from the source, is not contrary to conservation of water within the state and is not detrimental to the public welfare of the state, grant the application and issue a permit to the applicant to appropriate all or a part of the waters applied for, subject to the rights of all prior appropriators from the source.

F. If objections or protests have been filed within the time prescribed in the notice or if the state engineer is of the opinion that the permit should not be issued, the state engineer may deny the application without a hearing or, before the state engineer acts on the application, may order that a hearing be held. The state engineer shall notify the applicant of the action by certified mail sent to the address shown in the application.