The department by rule may prescribe the payment and collection of reasonable fees to issue permits or registration certificates for registering, licensing, or permitting solid waste generators, transporters, and treatment, storage, recycling, or disposal facilities. The fees must be based on the anticipated cost of filing and processing the application, taking action on the requested permit or registration certificate, and conducting a monitoring and inspection program to determine compliance or noncompliance with the permit or registration certificate. Any moneys collected for permit licensing or registration fees must be deposited in the department operating fund in the state treasury, and any expenditures from the fund are subject to appropriation by the legislative assembly. Applicants for special waste solid waste management facilities shall submit a minimum fee as follows:

Ask a legal question, get an answer ASAP!
Click here to chat with a lawyer about your rights.

Terms Used In North Dakota Code 23.1-08-10

  • Appropriation: The provision of funds, through an annual appropriations act or a permanent law, for federal agencies to make payments out of the Treasury for specified purposes. The formal federal spending process consists of two sequential steps: authorization
  • Rule: includes regulation. See North Dakota Code 1-01-49
  • State: when applied to the different parts of the United States, includes the District of Columbia and the territories. See North Dakota Code 1-01-49

1.    Twenty thousand dollars for any facility that receives on average one hundred tons [90718 kilograms] or more per day.

2.    Ten thousand dollars for any facility which receives on average more than ten tons [9071.80 kilograms] but less than one hundred tons [90718 kilograms] per day.