Public agencies shall notify the Commissioner of the Bureau of Labor and Industries in writing, on a form prescribed by the commissioner, whenever a contract subject to the provisions of ORS § 279C.800 to 279C.870 has been awarded. The notification shall be made within 30 days of the date that the contract is awarded. The notification shall include payment of the fee required under ORS § 279C.825 and a copy of the disclosure of first-tier subcontractors that was submitted under ORS § 279C.370. [2003 c.794 § 175; 2009 c.161 § 3]

Ask a legal question, get an answer ASAP!
Click here to chat with a lawyer about your rights.

Terms Used In Oregon Statutes 279C.835

  • Contract: A legal written agreement that becomes binding when signed.