If an application is pending under this chapter for a water right permit to use water for hydroelectric purposes or under ORS § 543.010 to 543.610 for a hydroelectric permit or license at the time the Water Resources Commission receives an application for an in-stream water right under ORS § 537.336 for the same stream or reach of the stream, the commission shall not take any action on the application for an in-stream water right until the commission issues a final order approving or denying the pending hydroelectric application. [1987 c.859 § 15]

Ask a legal question, get an answer ASAP!
Click here to chat with a lawyer about your rights.

 

MISCELLANEOUS