(1) Partial payment is allowed and may be made on contracts for construction and home improvement. An owner, contractor or subcontractor may withhold as retainage an amount equal to not more than five percent of the contract price of the work completed. Partial payment allowed under this subsection is not acceptance or approval of some of the work or a waiver of defects in the work.

Ask a business law question, get an answer ASAP!
Thousands of highly rated, verified business lawyers.
Click here to chat with a lawyer about your rights.

Terms Used In Oregon Statutes 701.420

  • Contract: A legal written agreement that becomes binding when signed.
  • Contractor: means any of the following:

    (a) A person that, for compensation or with the intent to sell, arranges or undertakes or offers to undertake or submits a bid to construct, alter, repair, add to, subtract from, improve, inspect, move, wreck or demolish, for another, a building, highway, road, railroad, excavation or other structure, project, development or improvement attached to real estate, or to do any part thereof. See Oregon Statutes 701.005

  • Escrow: Money given to a third party to be held for payment until certain conditions are met.
  • Home improvement: means a renovation, remodel, repair or alteration by a residential contractor to an existing owner-occupied:

    (A) Residence that is a site-built home;

    (B) Condominium, rental residential unit or other residential dwelling unit that is part of a larger structure, if the property interest in the unit is separate from the property interest in the larger structure;

    (C) Modular home constructed off-site;

    (D) Manufactured dwelling; or

    (E) Floating home, as defined in ORS § 830. See Oregon Statutes 701.005

(2)(a) The owner, contractor or subcontractor shall pay interest at the rate of one percent per month on the final payment due the contractor or subcontractor. The interest shall commence 30 days after the contractor or subcontractor has completed and the owner has accepted the work under the contract for construction for which the final payment is due. The interest shall run until the date when final payment is tendered to the contractor or subcontractor. When the contractor or subcontractor considers the work that the contractor or subcontractor is contracted to perform to be complete, the contractor or subcontractor shall notify the party to whom the contractor or subcontractor is responsible for performing the construction work under the contract. The party shall, within 15 days after receiving the notice, either accept the work or notify the contractor or subcontractor of work yet to be performed under the contract. If the party does not accept the work or does not notify the contractor or subcontractor of work yet to be performed within the time allowed, the interest required under this subsection shall commence 30 days after the end of the 15-day period.

(b) If the contract price exceeds $500,000, the owner, contractor or subcontractor shall place amounts withheld as retainage into an interest-bearing escrow account. Interest on the retainage amount accrues from the date the payment request is approved until the date the retainage is paid to the contractor or subcontractor to which it is due.

(3) When a contractor pays a subcontractor in full, including the amount the contractor withheld as retainage, the owner with whom the contractor has the contract shall pay the contractor, out of the amount that the owner withheld from the contractor as retainage, a sum equal to the amount of retainage that the contractor paid the subcontractor. The contractor shall notify the owner when the contractor pays a subcontractor in full under this section and the owner shall, within 15 days after receiving the notice, pay the contractor the amount due the contractor under this subsection. Interest on the amount due the contractor at the rate of one percent per month shall commence 30 days after the owner receives notice of full payment to the subcontractor. [1975 c.772 § 2; 2010 c.77 § 8; 2013 c.410 § 2; 2019 c.486 § 2]

 

See note under 701.410.