Ask a business law question, get an answer ASAP!
Thousands of highly rated, verified business lawyers.
Click here to chat with a lawyer about your rights.

Terms Used In South Carolina Code 58-27-1230

  • commission: means the Public Service Commission of this State. See South Carolina Code 58-27-10
  • electrical utility: includes municipalities to the extent of their business, property, rates, transactions, and operations without the corporate limits of the municipality, persons and corporations, their lessees, assignees, trustees, receivers, or other successors in interest owning or operating in this State equipment or facilities for generating, transmitting, delivering, or furnishing electricity for street, railway, or other public uses or for the production of light, heat, or power to or for the public for compensation; but it shall not include an electric cooperative or a consolidated political subdivision and shall not include a person, corporation, or municipality furnishing electricity only to himself or itself, their residents, employees, or tenants when such current is not resold or used by others. See South Carolina Code 58-27-10
  • municipality: includes a city, town, county, township, or any other corporation existing, created, or organized as a governmental unit under the Constitution or laws of this State except a consolidated political subdivision. See South Carolina Code 58-27-10
  • public: means the public generally or any limited portion of the public, including a person, corporation, or municipality. See South Carolina Code 58-27-10
No electrical utility, except a municipality within its corporate limits, shall hereafter begin the construction or operation of any electrical utility plant or system or of any extension thereof, except those ordered by the Commission under the provisions of § 58-27-1210, without first obtaining from the Commission a certificate that public convenience and necessity require or will require such construction or operation. But unless such construction or operation has been commenced under a limited or conditional certificate of authority as provided by § 58-27-1260, this section shall not be construed to require any such electrical utility to secure a certificate (a) for any extension within any municipality or district within which it had lawfully commenced operations prior to April 8, 1932, (b) for an extension within or to territory already served by it, necessary in the ordinary course of its business or (c) for an extension into territory contiguous to that already occupied by it and not receiving similar service from another electrical utility. No electrical utility, except a municipality within its corporate limits, shall exercise any right or privilege under any franchise or permit, the exercise of which has been suspended or discontinued for more than one year, without first obtaining from the Commission a certificate that public convenience and necessity require the exercise of such right or privilege.