South Carolina Code 58-36-60. Notice of intent to excavate or demolish; expiration of notice; reasonable time to remove or protect facilities; compliance by excavators
(B) Notice given pursuant to subsection (A) shall expire within fifteen working days after the date of notice. No excavation or demolition may continue after this fifteen-day period unless the person responsible for the excavation or demolition provides a subsequent notice pursuant to subsection (A).
Terms Used In South Carolina Code 58-36-60
- Damages: Money paid by defendants to successful plaintiffs in civil cases to compensate the plaintiffs for their injuries.
(C) The notice to the notification center must contain:
(1) the name, address, and telephone number of the person providing the notice;
(2) the anticipated start date of the proposed excavation or demolition;
(3) the anticipated duration of the proposed excavation or demolition;
(4) the type of proposed excavation or demolition to be conducted;
(5) the location of the proposed excavation or demolition, not to exceed one-quarter mile in geographical length, or five adjoining addresses; and
(6) whether or not explosives are to be used in the proposed excavation or demolition.
(D) When demolition of a building is proposed, operators shall be given reasonable time to remove or protect their facilities before demolition is commenced.
(E) An excavator must comply with the following:
(1) When the excavation site cannot be clearly and adequately identified within the area described in the notice, the excavator must designate the route, specific area to be excavated, or both, by pre-marking before the operator performs a locate. Premarking must be made with white paint, flags, or stakes.
(2) Check the notification center’s positive response system prior to excavating or demolishing to ensure that all operators have responded and that all facilities that may be affected by the proposed excavation or demolition have been marked.
(3) Plan the excavation or demolition to avoid damage to or minimize interference with facilities in and near the construction area.
(4) Excavation or demolition may begin prior to the specified waiting period if the excavator has confirmed that all operators responded with an appropriate positive response.
(5) If an operator declares extraordinary circumstances, the excavator must not excavate or demolish until after the time and date that the operator provided in its response.
(6) An operator’s failure to respond to the positive response system does not prohibit the excavator from proceeding, provided there are no visible indications of a facility, such as a pole, marker, pedestal, or valve at the proposed excavation or demolition site. However, if the excavator is aware of or observes indications of an unmarked facility, the excavator must not begin excavation or demolition until an additional call is made to the notification center detailing the facility, and an arrangement is made for the facility to be marked by the operator within three hours from the time the additional call is received by the notification center.
(7) Beginning on the date provided in the excavator’s notice to the notification center, the excavator shall preserve the staking, marking, or other designation until no longer required. When a mark is no longer visible, but the work continues in the vicinity of the facility, the excavator must request a re-mark from the notification center to ensure the protection of the facility.
(8) The excavator shall notify the notification center’s positive response system when the excavation or demolition is complete.
(9) An excavator may not perform any excavation or demolition within the tolerance zone unless the following conditions are met:
(a) no use of mechanized equipment, except non-invasive equipment specifically designed or intended to protect the integrity of the facility, within the marked tolerance zone of an existing facility until:
(i) the excavator has visually identified the precise location of the facility, or has visually confirmed that no facility is present up to the depth of excavation; and
(ii) reasonable precautions are taken to avoid any substantial weakening of the facility’s structural or lateral support, or both, or penetration or destruction of the facilities or their protective coatings.
Mechanical means may be used, as necessary, for initial penetration and removal of pavement or other materials requiring use of mechanical means of excavation and then only to the depth of the pavement or other materials. For parallel type excavations within the tolerance zone, the existing facility shall be visually identified at intervals not to exceed fifty feet along the line of excavation to avoid damages. The excavator shall exercise due care at all times to protect the facilities when exposing these facilities;
(b) maintain clearance between a facility and the cutting edge or point of any mechanized equipment, taking into account the known limit of control of such cutting edge or point, as may be reasonably necessary to avoid damage to such facility; and
(c) provide support for facilities in and near the excavation or demolition area, including backfill operations, as may be reasonably required by the operator for the protection of such facilities.