If the provisions of §§ 44-9-50 and 44-9-51 are first invoked, no subsubcontractor or supplier to subcontractors is entitled to extend, pursuant to § 44-9-15, a lien created pursuant to subdivision 44-9-1(1), unless the subsubcontractor or supplier has first provided notice of furnishing labor or materials by certified or registered mail to the contractor identified in the notice of project commencement and has provided a copy of the notice to the owner of record. Notice pursuant to this section shall be made not later than sixty days after doing the last of such work, or furnishing the last item of such skill, services, material, or machinery, and the post office receipt for mailing such notice shall be attached to the lien and filed in the office of register of deeds. Such notice of furnishing labor or materials shall include:

(1) The name of the subsubcontractor or supplier who claims payment;

Ask a real estate law question, get an answer ASAP!
Thousands of highly rated, verified real estate lawyers.
Specialties include: All Real Estate Law, Landlord and Tenant Law, Foreclosure, Homeowners' Association, Trespassing, Property Law, General Legal and more.
Click here to chat with a lawyer about your rights.

Terms Used In South Dakota Codified Laws 44-9-53

  • Contract: A legal written agreement that becomes binding when signed.
  • Lien: A claim against real or personal property in satisfaction of a debt.
  • Person: includes natural persons, partnerships, associations, cooperative corporations, limited liability companies, and corporations. See South Dakota Codified Laws 2-14-2

(2) The name of the person with whom the claimant contracted or by whom the claimant was employed;

(3) A description of the labor, services, or materials furnished and the contract price or value thereof. Materials specifically fabricated by a person other than the one giving notice and contract price or value thereof shall be separately stated in the notice;

(4) A description of the project, sufficient for identification;

(5) The date when the first and last item of labor or materials was actually furnished or scheduled to be furnished; and

(6) The amount claimed to be due, if any.

Any person who gives notice in accordance with this section may extend a lien as provided in § 44-9-15.

This section does not apply to claims of individual laborers when the amount of their lien is less than two thousand dollars.

Source: SL 1999, ch 217, § 4.