(a) If a prime contractor has performed in accordance with the prime contractor’s written contract with the owner, then the owner shall pay to the prime contractor the full amount earned by the prime contractor, less only those amounts withheld in accordance with § 66-34-203. The payment must be made in accordance with the schedule for payments established within the contract and within thirty (30) days after application for payment is timely submitted by the prime contractor to the owner, in accordance with the schedule.

Ask a legal question, get an answer ASAP!
Click here to chat with a lawyer about your rights.

Terms Used In Tennessee Code 66-34-202

  • Contract: A legal written agreement that becomes binding when signed.
  • written: includes printing, typewriting, engraving, lithography, and any other mode of representing words and letters. See Tennessee Code 1-3-105
(b) Failure of an architect, engineer, or other agent employed by the owner to review and approve an application for payment for work which has been performed in accordance with the contract does not excuse the owner from making payment in accordance with this chapter. This section does not require payment for work not performed if an architect, engineer, or other agent has certified that a contractor has not completed performance for a portion of work covered by the application for payment.