Tennessee Code 66-34-602 – Nonpayment – Notice of intent to seek relief under chapter – Remedies – Attorney’s fees – Bond
Terms Used In Tennessee Code 66-34-602
- Code: includes the Tennessee Code and all amendments and revisions to the code and all additions and supplements to the code. See Tennessee Code 1-3-105
- Contract: A legal written agreement that becomes binding when signed.
- Equitable: Pertaining to civil suits in "equity" rather than in "law." In English legal history, the courts of "law" could order the payment of damages and could afford no other remedy. See damages. A separate court of "equity" could order someone to do something or to cease to do something. See, e.g., injunction. In American jurisprudence, the federal courts have both legal and equitable power, but the distinction is still an important one. For example, a trial by jury is normally available in "law" cases but not in "equity" cases. Source: U.S. Courts
- Lawsuit: A legal action started by a plaintiff against a defendant based on a complaint that the defendant failed to perform a legal duty, resulting in harm to the plaintiff.
- Property: includes both personal and real property. See Tennessee Code 1-3-105
- written: includes printing, typewriting, engraving, lithography, and any other mode of representing words and letters. See Tennessee Code 1-3-105
This letter shall serve as notice pursuant to the Tennessee Prompt Pay Act, Tenn. Code Ann. §§ 66-34-101 et seq., of [prime contractor or remote contractor]’s intent to seek relief under the Prompt Pay Act. [Prime contractor or remote contractor] furnished [description of labor, materials, or services furnished] in furtherance of improvements to real property located at [property description] pursuant to its written contract with [lender, owner, prime contractor, or remote contractor]. [Prime contractor or remote contractor] first furnished labor, materials, or services on [insert first date] and [“is still continuing to perform” or “last furnished labor, materials, or services on (insert date)”]. If [owner, prime contractor, and/or remote contractor] fail(s) to make payment, arrange for payment, or provide a response setting forth adequate legal reasons for the failure to make payment to [prime contractor or remote contractor] within ten (10) days of your receipt of this letter, then [prime contractor or remote contractor] may, in addition to all other remedies at law or in equity, file a lawsuit for equitable relief, including injunctive relief, for continuing violations of this chapter.