Michigan Laws 460.564 – Construction plan
Current as of: 2024 | Check for updates
|
Other versions
(1) If an electric utility that has 50,000 or more residential customers in this state, affiliated transmission company, or an independent transmission company plans to construct a major transmission line in this state in the 5 years after planning commences, the electric utility, affiliated transmission company, or independent transmission company shall submit a construction plan to the commission. An electric utility with fewer than 50,000 residential customers in this state may submit a plan under this section. A plan shall include all of the following:
(a) The general location and size of all major transmission lines to be constructed in the 5 years after planning commences.
Terms Used In Michigan Laws 460.564
- Affiliated transmission company: means a person, partnership, corporation, association, or other legal entity, or its successors or assigns, which has fully satisfied the requirements to join a regional transmission organization as determined by the federal energy regulatory commission, is engaged in this state in the transmission of electricity using facilities it owns that were transferred to the entity by an electric utility that was engaged in the generation, transmission, and distribution of electricity in this state on December 31, 2000, and is not independent of an electric utility or an affiliate of the utility, generating or distributing electricity to retail customers in this state. See Michigan Laws 460.562
- Commission: means the Michigan public service commission. See Michigan Laws 460.562
- Construction: means any substantial action taken on a route constituting placement or erection of the foundations or structures supporting a transmission line. See Michigan Laws 460.562
- Electric utility: means a person, partnership, corporation, association, or other legal entity whose transmission or distribution of electricity the commission regulates under 1909 PA 106, MCL 460. See Michigan Laws 460.562
- Independent transmission company: means a person, partnership, corporation, association, or other legal entity, or its successors or assigns, engaged in this state in the transmission of electricity using facilities it owns that have been divested to the entity by an electric utility that was engaged in the generation, transmission, and distribution of electricity in this state on December 31, 2000, and is independent of an electric utility or an affiliate of the utility, generating or distributing electricity to retail customers in this state. See Michigan Laws 460.562
- Major transmission line: means a transmission line of 5 miles or more in length wholly or partially owned by an electric utility, affiliated transmission company, or independent transmission company through which electricity is transferred at system bulk supply voltage of 345 kilovolts or more. See Michigan Laws 460.562
- Municipality: means a city, township, or village. See Michigan Laws 460.562
- state: when applied to the different parts of the United States, shall be construed to extend to and include the District of Columbia and the several territories belonging to the United States; and the words "United States" shall be construed to include the district and territories. See Michigan Laws 8.3o
- Transmission line: means all structures, equipment, and real property necessary to transfer electricity at system bulk supply voltage of 100 kilovolts or more. See Michigan Laws 460.562
(b) Copies of relevant bulk power transmission information filed by the electric utility, affiliated transmission company, or independent transmission company with any state or federal agency, national electric reliability coalition, or regional electric reliability coalition.
(c) Additional information required by commission rule or order that directly relates to the construction plan.
(2) At the same time the electric utility, affiliated transmission company, or independent transmission company submits a construction plan to the commission under subsection (1), the electric utility, affiliated transmission company, or independent transmission company shall provide a copy of the construction plan to each municipality in which construction of the planned major transmission line is intended.