(a) The commission is responsible for directing final payment for work done on each project. If on final inspection of a project it determines that the plans, specifications, contract, or change orders for the project have not been fully complied with, the commission shall, until compliance has occurred or adjustments satisfactory to the commission have been made, refuse to direct final payment.
(b) Final inspection consists of an on-site inspection by the design professional, a commission representative, a using agency representative, and at least one representative of each contractor.

Ask a legal question, get an answer ASAP!
Click here to chat with a lawyer about your rights.

Terms Used In Texas Government Code 2166.356

  • Contract: A legal written agreement that becomes binding when signed.
  • Written: includes any representation of words, letters, symbols, or figures. See Texas Government Code 311.005

(c) The commission shall schedule the final inspection not later than the 10th day after the date the design professional notifies the commission that the contract has been performed according to the plans and specifications.
(d) On completion of the project, the commission shall release the project to the using agency.
(e) The commission is responsible for inspecting the project before the expiration of the guarantee period to observe defects that may appear not later than the first anniversary of the date the contract is completed. The commission shall give prompt written notice to the contractor of defects that are due to faulty materials or work. This subsection does not require the contractor to assume responsibility for or guarantee defects other than those due to faulty materials or work or failure on the contractor’s part to adhere to the contract documents.