Texas Property Code 28.002 – Prompt Pay Required
(a) If an owner or a person authorized to act on behalf of the owner receives a written payment request from a contractor for an amount that is allowed to the contractor under the contract for properly performed work or suitably stored or specially fabricated materials, the owner shall pay the amount to the contractor, less any amount withheld as authorized by statute, not later than the 35th day after the date the owner receives the request.
(b) A contractor who receives a payment under Subsection (a) or otherwise from an owner in connection with a contract to improve real property shall pay each of its subcontractors the portion of the owner’s payment, including interest, if any, that is attributable to work properly performed or materials suitably stored or specially fabricated as provided under the contract by that subcontractor, to the extent of that subcontractor’s interest in the owner’s payment. The payment required by this subsection must be made not later than the seventh day after the date the contractor receives the owner’s payment.
Terms Used In Texas Property Code 28.002
- Contract: A legal written agreement that becomes binding when signed.
- Person: includes corporation, organization, government or governmental subdivision or agency, business trust, estate, trust, partnership, association, and any other legal entity. See Texas Government Code 311.005
- Property: means real and personal property. See Texas Government Code 311.005
- Real property: Land, and all immovable fixtures erected on, growing on, or affixed to the land.
- Statute: A law passed by a legislature.
- Written: includes any representation of words, letters, symbols, or figures. See Texas Government Code 311.005
(c) A subcontractor who receives a payment under Subsection (b) or otherwise from a contractor in connection with a contract to improve real property shall pay each of its subcontractors the portion of the payment, including interest, if any, that is attributable to work properly performed or materials suitably stored or specially fabricated as provided under the contract by that subcontractor, to the extent of that subcontractor’s interest in the payment. The payment required by this subsection must be made not later than the seventh day after the date the subcontractor receives the contractor’s payment.