(a) The board shall adopt rules necessary to administer this subchapter, including rules establishing procedures for the application for and award of loans, the distribution of loans, the investment of funds, and the administration of loans and the fund.
(b) The board may not release from the fund money for the construction phase of parts of projects proposing surface water or groundwater development until the executive administrator makes a written finding that a rural political subdivision:
(1) has the necessary water right authorizing it to appropriate and use the water that the project will provide, if the rural political subdivision is proposing surface water development; or
(2) has the right to use water that the project will provide, if the rural political subdivision is proposing groundwater development.

Ask a legal question, get an answer ASAP!
Click here to chat with a lawyer about your rights.

Terms Used In Texas Water Code 15.995


(c) In passing on an application from a rural political subdivision for financial assistance, the board shall consider:
(1) the needs of the area to be served by the project, the benefit of the project to the area, the relationship of the project to the overall state water needs, and the relationship of the project to the state water plan; and
(2) the availability of revenue to the rural political subdivision from all sources for the ultimate repayment of the cost of the water supply project, including all interest.
(d) The board by resolution may approve an application if, after considering the factors listed in Subsection (c) and other relevant factors, the board finds that:
(1) the public interest is served by state assistance for the project; and
(2) the revenue or taxes pledged by the rural political subdivision will be sufficient to meet all the obligations assumed by the rural political subdivision during the succeeding period of not more than 50 years.
(e) An application from a rural political subdivision for financial assistance under this subchapter must comply with the requirements of § 16.4021.
(f) Sections 17.183-17.187 apply to the construction of projects funded pursuant to this subchapter.