(1) After the full amount owing under a preconstruction or construction lien, including costs and cancellation fees, has been paid, a person interested in the property that is the subject of the lien may request the claimant to submit for recording with the office of each applicable county recorder a cancellation of the lien.

Ask a real estate law question, get an answer ASAP!
Thousands of highly rated, verified real estate lawyers.
Specialties include: All Real Estate Law, Landlord and Tenant Law, Foreclosure, Homeowners' Association, Trespassing, Property Law, General Legal and more.
Click here to chat with a lawyer about your rights.

Terms Used In Utah Code 38-1a-803

  • Applicable county recorder: means the office of the recorder of each county in which any part of the property on which a claimant claims or intends to claim a preconstruction or construction lien is located. See Utah Code 38-1a-102
  • Claimant: means a person entitled to claim a preconstruction or construction lien. See Utah Code 38-1a-102
  • Construction lien: means a lien under this chapter for construction work. See Utah Code 38-1a-102
  • Damages: Money paid by defendants to successful plaintiffs in civil cases to compensate the plaintiffs for their injuries.
  • Lien: A claim against real or personal property in satisfaction of a debt.
  • Person: means :
         (24)(a) an individual;
         (24)(b) an association;
         (24)(c) an institution;
         (24)(d) a corporation;
         (24)(e) a company;
         (24)(f) a trust;
         (24)(g) a limited liability company;
         (24)(h) a partnership;
         (24)(i) a political subdivision;
         (24)(j) a government office, department, division, bureau, or other body of government; and
         (24)(k) any other organization or entity. See Utah Code 68-3-12.5
  • Property: includes both real and personal property. See Utah Code 68-3-12.5
(2) Within 10 days after receiving a request under Subsection (1), the claimant shall submit to the office of each applicable county recorder a cancellation of the preconstruction or construction lien, as applicable.
(3) A claimant who fails to submit a cancellation within the time prescribed in Subsection (2) is liable to the person who requested the cancellation for $100 for each day after the time prescribed in Subsection (2) that the cancellation is not submitted, or the person’s actual damages, whichever is greater.