Utah Code 73-5a-205. Approvals void after one year if construction delayed — Exceptions
Current as of: 2024 | Check for updates
|
Other versions
(1) Any approval granted under Section 73-5a-203 is void one year after the date of approval if construction has not started.
Terms Used In Utah Code 73-5a-205
- State: when applied to the different parts of the United States, includes a state, district, or territory of the United States. See Utah Code 68-3-12.5
(2) The state engineer may extend the approval in one year increments:
(2)(a) upon a showing of reasonable cause for delay; and
(2)(b) provided state-of-the-art design criteria has not changed in the intervening period.