Virginia Code 43-10: Sufficiency of memorandum, affidavit and notice required by § 43-9
The memorandum, affidavit and notice required by § 43-9 shall be sufficient if substantially in form and effect as follows:
Terms Used In Virginia Code 43-10
- Affidavit: A written statement of facts confirmed by the oath of the party making it, before a notary or officer having authority to administer oaths.
- general contractor: includes contractors, laborers, mechanics, and persons furnishing materials, who contract directly with the owner, and the term "subcontractor" includes all such contractors, laborers, mechanics, and persons furnishing materials, who do not contract with the owner but with the general contractor. See Virginia Code 43-1
- Lien: A claim against real or personal property in satisfaction of a debt.
- Real property: Land, and all immovable fixtures erected on, growing on, or affixed to the land.
Memorandum for Mechanic’s Lien Claimed by Sub-subcontractor.
Name of owner: ___________________________________________________________________________
Address of owner: ___________________________________________________________________________
Name of general contractor (if any) and subcontractor:
___________________________________________________________________________
Name of claimant: ___________________________________________________________________________
Address of claimant: ___________________________________________________________________________
Contractor license or certificate number of claimant
(if applicable): ___________________________________________________________________________
Issuance date of license or certificate
(if applicable): ___________________________________________________________________________
Expiration date of license or certificate
(if applicable): ___________________________________________________________________________
If no contractor license or certificate number is included, the claimant certifies that such a valid license or certificate is not required by law for the work done for which the benefit of a lien is claimed.
1. Type of materials or services furnished: ___________________________________________________________________________
___________________________________________________________________________
2. Amount claimed: $ ___________________________________________________________________________
If any part of the Amount claimed is not due as of the date of this mechanic’s lien, identify the date or event upon which it will be due, and the sum(s) to which the due date(s) or event(s) apply: ___________________________________________________________________________
3. Type of structure on which work done or materials furnished: ___________________________________________________________________________
___________________________________________________________________________
4. Brief description and location of real property: ___________________________________________________________________________
___________________________________________________________________________
5. Date from which interest on above amount is claimed:
Date: ____________________________
It is the intent of the claimant to claim the benefit of a lien.
____________________________ (Name of claimant).
______________ (Signature of claimant or agent for claimant).
Affidavit.
State of Virginia,
County (or city) of ________________________, to wit:
I, ___________________________________________________________________________ (notary or other officer) for the county (or city)
aforesaid do certify that ___________________________________________ claimant, or ___________________________________________, agent for claimant, this day made oath before me in my county (or city) aforesaid that _______________ is justly indebted to claimant in the sum of __________ dollars for the consideration stated in the foregoing memorandum, and that the same is payable as therein stated.
Given under my hand this the ……………. day of ……………, 20….
________________________________________ (Notary Public or
Magistrate, et cetera.)
Notice.
To __________________________ (owner) and __________________________ (general contractor):
You are hereby notified that ___________________________________________________________________________ , a subcontractor under you,
said ___________________________________________________________________________ (general contractor) for the construction (or removal,
etc.,) of a ___________________________________________________________________________ (describe structure) for you, or on property owned by
you, said ___________________________________________________________________________ (owner) is indebted to me in the sum of ………….
…………….. dollars ($ ______________) with interest thereon from the …. day of ……., 20…, for work done (or materials furnished) in and about the construction (or removal, etc.,) of _________________________ (naming structure), situate in the county (or city) of _______________ Virginia, and that I have duly recorded a mechanic’s lien for the same.
Given under my hand this the ……………… day of ……………, 20…….
__________________________________________________ (Sub-subcontractor).
Code 1919, § 6429; 1968, c. 568; 1984, c. 647; 2007, c. 504; 2013, c. 293; 2019, c. 243.