A. Except as provided in § 62.1-44.15:31 for a land-disturbing activity conducted by a state agency, federal entity, or other specified entity, no person shall engage in any land-disturbing activity until (i) he has submitted to the VESCP authority an erosion and sediment control plan for the land-disturbing activity and the plan has been reviewed and approved and (ii) where Virginia Pollutant Discharge Elimination System permit coverage is required, the VESCP authority has obtained evidence of such permit coverage from the Department‘s online reporting system prior to issuing its land-disturbance approval. A VESCP authority may enter into an agreement with an adjacent VESCP or VESMP authority regarding the administration of multijurisdictional projects specifying who shall be responsible for all or part of the administrative procedures. Should adjacent authorities fail to come to such an agreement, each shall be responsible for administering the area of the multijurisdictional project that lies within its jurisdiction. Where the land-disturbing activity results from the construction of a (a) single-family residence or (b) farm building or structure on a parcel of land with a total impervious cover percentage, including the impervious cover from the farm building or structure to be constructed, of less than five percent, an agreement in lieu of a plan may be substituted for an erosion and sediment control plan if executed by the VESCP authority.

Ask a legal question, get an answer ASAP!
Click here to chat with a lawyer about your rights.

Terms Used In Virginia Code 62.1-44.15:55

  • Agreement in lieu of a plan: means a contract between the VESCP authority and the owner that specifies conservation measures that must be implemented in the construction of a (i) single-family detached residential structure or (ii) farm building or structure on a parcel of land with a total impervious cover percentage, including the impervious cover from the farm building or structure to be constructed, of less than five percent; this contract may be executed by the VESCP authority in lieu of a formal site plan. See Virginia Code 62.1-44.15:51
  • Applicant: means any person submitting an erosion and sediment control plan for approval in order to obtain authorization for land-disturbing activities to commence. See Virginia Code 62.1-44.15:51
  • Board: means the State Water Control Board. See Virginia Code 62.1-44.3
  • Certificate: means any certificate or permit issued by the Department. See Virginia Code 62.1-44.3
  • Contract: A legal written agreement that becomes binding when signed.
  • Department: means the Department of Environmental Quality. See Virginia Code 62.1-44.15:51
  • Erosion impact area: means an area of land that is not associated with a current land-disturbing activity but is subject to persistent soil erosion resulting in the delivery of sediment onto neighboring properties or into state waters. See Virginia Code 62.1-44.15:51
  • Evidence: Information presented in testimony or in documents that is used to persuade the fact finder (judge or jury) to decide the case for one side or the other.
  • farm: means any person that obtains at least 51 percent of its annual gross income from agricultural operations and produces the agricultural waste used as feedstock for the waste-to-energy technology, (ii) "agricultural waste" means biomass waste materials capable of decomposition that are produced from the raising of plants and animals during agricultural operations, including animal manures, bedding, plant stalks, hulls, and vegetable matter, and (iii) "waste-to-energy technology" means any technology, including but not limited to a methane digester, that converts agricultural waste into gas, steam, or heat that is used to generate electricity on-site. See Virginia Code 1-222.1
  • Farm building or structure: means the same as that term is defined in § 36-97 and also includes any building or structure used for agritourism activity, as defined in § Virginia Code 62.1-44.15:51
  • Jurisdiction: (1) The legal authority of a court to hear and decide a case. Concurrent jurisdiction exists when two courts have simultaneous responsibility for the same case. (2) The geographic area over which the court has authority to decide cases.
  • Land-disturbance approval: means an approval allowing a land-disturbing activity to commence issued by (i) a Virginia Erosion and Stormwater Management Program authority after the requirements of § Virginia Code 62.1-44.3
  • land-disturbing activity: means any man-made change to the land surface that may result in soil erosion or has the potential to change its runoff characteristics, including the clearing, grading, excavating, transporting, and filling of land. See Virginia Code 62.1-44.15:51
  • Owner: means the same as provided in § Virginia Code 62.1-44.15:51
  • Person: means any individual, partnership, firm, association, joint venture, public or private corporation, trust, estate, commission, board, public or private institution, utility, cooperative, county, city, town, or other political subdivision of the Commonwealth, governmental body, including a federal or state entity as applicable, any interstate body, or any other legal entity. See Virginia Code 62.1-44.15:51
  • plan: means a document containing material for the conservation of soil and water resources of a unit or group of units of land. See Virginia Code 62.1-44.15:51
  • state agency: means the same as that term is defined in § Virginia Code 1-206
  • United States: includes the 50 states, the District of Columbia the Commonwealth of Puerto Rico, Guam, the Northern Mariana Islands and the United States Virgin Islands. See Virginia Code 1-255
  • VESCP: means a program approved by the Board that has been established by a VESCP authority for the effective control of soil erosion, sediment deposition, and nonagricultural runoff associated with a land-disturbing activity to prevent the unreasonable degradation of properties, stream channels, waters, and other natural resources and shall include such items where applicable as local ordinances, rules, policies and guidelines, technical materials, and requirements for plan review, inspection, and evaluation consistent with the requirements of this article. See Virginia Code 62.1-44.15:51
  • VESCP authority: means a locality approved by the Board to operate a Virginia Erosion and Sediment Control Program. See Virginia Code 62.1-44.15:51
  • Wetlands: means those areas that are inundated or saturated by surface or groundwater at a frequency and duration sufficient to support, and that under normal circumstances do support, a prevalence of vegetation typically adapted for life in saturated soil conditions. See Virginia Code 62.1-44.3

B. The VESCP authority shall review erosion and sediment control plans submitted to it and grant written approval within 60 days of the receipt of the plan if it determines that the plan meets the requirements of this article and the Board‘s regulations and if the person responsible for carrying out the plan certifies that he will properly perform the erosion and sediment control measures included in the plan and shall comply with the provisions of this article. In addition, as a prerequisite to engaging in the land-disturbing activities shown on the approved plan, the person responsible for carrying out the plan shall provide the name of an individual holding a certificate to the VESCP authority, as provided by § 62.1-44.15:52, who will be in charge of and responsible for carrying out the land-disturbing activity. However, any VESCP authority may waive the certificate requirement for an agreement in lieu of a plan. If a violation occurs during the land-disturbing activity, then the person responsible for carrying out the agreement in lieu of a plan shall correct the violation and provide the name of an individual holding a certificate, as provided by § 62.1-44.15:52. Failure to provide the name of an individual holding a certificate prior to engaging in land-disturbing activities may result in revocation of the approval of the plan and the person responsible for carrying out the plan shall be subject to the penalties provided in this article.

When a plan is determined to be inadequate, written notice of disapproval stating the specific reasons for disapproval shall be communicated to the applicant within 45 days. The notice shall specify the modifications, terms, and conditions that will permit approval of the plan. If no action is taken by the VESCP authority within the time specified in this subsection, the plan shall be deemed approved and the person authorized to proceed with the proposed activity. The VESCP authority shall act on any erosion and sediment control plan that has been previously disapproved within 45 days after the plan has been revised, resubmitted for approval, and deemed adequate.

C. The VESCP authority may require changes to an approved plan in the following cases:

1. Where inspection has revealed that the plan is inadequate to satisfy applicable regulations; or

2. Where the person responsible for carrying out the approved plan finds that because of changed circumstances or for other reasons the approved plan cannot be effectively carried out, and proposed amendments to the plan, consistent with the requirements of this article and associated regulations, are agreed to by the VESCP authority and the person responsible for carrying out the plan.

D. In order to prevent further erosion, a VESCP authority may require approval of an erosion and sediment control plan for any land identified by the VESCP authority as an erosion impact area.

E. For the purposes of subsections A and B, when land-disturbing activity will be required of a contractor performing construction work pursuant to a construction contract, the preparation, submission, and approval of an erosion and sediment control plan shall be the responsibility of the owner.

F. Notwithstanding any other provisions of this article, the following activities are not required to comply with the requirements of this article unless otherwise required by federal law:

1. Disturbance of a land area of less than 10,000 square feet in size or less than 2,500 square feet in an area designated as a Chesapeake Bay Preservation Area pursuant to the Chesapeake Bay Preservation Act (§ 62.1-44.15:67 et seq.). However, the governing body of the program authority may reduce this exception to a smaller area of disturbed land or qualify the conditions under which this exception shall apply;

2. Minor land-disturbing activities such as home gardens and individual home landscaping, repairs, and maintenance work;

3. Installation, maintenance, or repair of any individual service connection;

4. Installation, maintenance, or repair of any underground utility line when such activity occurs on an existing hard surfaced road, street, or sidewalk, provided the land-disturbing activity is confined to the area of the road, street, or sidewalk that is hard surfaced;

5. Installation, maintenance, or repair of any septic tank line or drainage field unless included in an overall plan for land-disturbing activity relating to construction of the building to be served by the septic tank system;

6. Permitted surface or deep mining operations and projects, or oil and gas operations and projects conducted pursuant to Title 45.2;

7. Clearing of lands specifically for bona fide agricultural purposes; the management, tilling, planting, or harvesting of agricultural, horticultural, or forest crops; livestock feedlot operations; agricultural engineering operations, including construction of terraces, terrace outlets, check dams, desilting basins, dikes, ponds, ditches, strip cropping, lister furrowing, contour cultivating, contour furrowing, land drainage, and land irrigation; or as additionally set forth by the Board in regulations. However, this exception shall not apply to harvesting of forest crops unless the area on which harvesting occurs is reforested artificially or naturally in accordance with the provisions of Chapter 11 of Title 10.1 or is converted to bona fide agricultural or improved pasture use as described in subsection B of § 10.1-1163;

8. Installation of fence and sign posts or telephone and electric poles and other kinds of posts or poles;

9. Shoreline erosion control projects on tidal waters when all of the land-disturbing activities are within the regulatory authority of and approved by local wetlands boards, the Marine Resources Commission, or the United States Army Corps of Engineers; however, any associated land that is disturbed outside of this exempted area shall remain subject to this article and the regulations adopted pursuant thereto;

10. Land-disturbing activities in response to a public emergency where the related work requires immediate authorization to avoid imminent endangerment to human health or the environment. In such situations, the VESMP authority shall be advised of the disturbance within seven days of commencing the land-disturbing activity, and compliance with the administrative requirements of subsection A is required within 30 days of commencing the land-disturbing activity;

11. Discharges to a sanitary sewer or a combined sewer system that are not from a land-disturbing activity; and

12. Repair or rebuilding of the tracks, rights-of-way, bridges, communication facilities, and other related structures and facilities of a railroad company.

1973, c. 486, § 21-89.6; 1979, c. 432; 1988, cc. 732, 891, § 10.1-563; 1993, c. 925; 1999, c. 555; 2001, c. 490; 2003, cc. 827, 966; 2006, c. 466; 2008, c. 23; 2011, cc. 720, 721; 2012, cc. 785, 819; 2013, cc. 756, 793; 2016, cc. 68, 758; 2023, cc. 48, 49; 2024, cc. 5, 104.