Washington Code 80.04.430 – Findings of commission prima facie correct
Current as of: 2023 | Check for updates
|
Other versions
Whenever the commission has issued or promulgated any order or rule, in any writ of review brought by a public service company to determine the reasonableness of such order or rule, the findings of fact made by the commission shall be prima facie correct, and the burden shall be upon said public service company to establish the order or rule to be unreasonable or unlawful.
[ 1961 c 14 § 80.04.430. Prior: 1911 c 117 § 100; RRS § 10449.]
Terms Used In Washington Code 80.04.430
- Commission: means the utilities and transportation commission. See Washington Code 80.04.010
- Public service company: includes every gas company, electrical company, telecommunications company, wastewater company, and water company. See Washington Code 80.04.010
- Writ: A formal written command, issued from the court, requiring the performance of a specific act.