Washington Code 80.50.330 – Preapplication — Siting electrical transmission facilities — Corridors
Current as of: 2023 | Check for updates
|
Other versions
(1) For applications to site electrical transmission facilities, the council shall conduct a preapplication process pursuant to rules adopted by the council to govern such process, receive applications as prescribed in RCW 80.50.071, and conduct public meetings pursuant to RCW 80.50.090.
Terms Used In Washington Code 80.50.330
- Applicant: means any person who makes application for a site certification pursuant to the provisions of this chapter. See Washington Code 80.50.020
- Application: means any request for approval of a particular site or sites filed in accordance with the procedures established pursuant to this chapter, unless the context otherwise requires. See Washington Code 80.50.020
- Certification: means a binding agreement between an applicant and the state which shall embody compliance to the siting guidelines, in effect as of the date of certification, which have been adopted pursuant to RCW 80. See Washington Code 80.50.020
- Council: means the energy facility site evaluation council created by RCW 80. See Washington Code 80.50.020
- Electrical transmission facilities: means electrical power lines and related equipment. See Washington Code 80.50.020
- Facilities: means lines, conduits, ducts, poles, wires, cables, cross-arms, receivers, transmitters, instruments, machines, appliances, instrumentalities and all devices, real estate, easements, apparatus, property and routes used, operated, owned or controlled by any telecommunications company to facilitate the provision of telecommunications service. See Washington Code 80.04.010
- Preapplicant: means a person considering applying for a site certificate agreement for any facility. See Washington Code 80.50.020
- Preapplication process: means the process which is initiated by written correspondence from the preapplicant to the council, and includes the process adopted by the council for consulting with the preapplicant and with federally recognized tribes, cities, towns, and counties prior to accepting applications for any facility. See Washington Code 80.50.020
- Site: means any proposed or approved location of an energy facility, alternative energy resource, clean energy product manufacturing facility, or electrical transmission facility. See Washington Code 80.50.020
- Transmission facility: means any of the following together with their associated facilities:
Washington Code 80.50.020
(2) The council shall consider and may recommend certification of electrical transmission facilities in corridors designated for this purpose by affected cities, towns, or counties:
(a) Where the jurisdictions have identified electrical transmission facility corridors as part of their land use plans and zoning maps based on policies adopted in their plans;
(b) Where the proposed electrical transmission facility is consistent with any adopted development regulations that govern the siting of electrical transmission facilities in such corridors; and
(c) Where contiguous jurisdictions and jurisdictions in which related regional electrical transmission facilities are located have either prior to or during the preapplication process undertaken good faith efforts to coordinate the locations of their corridors consistent with RCW 36.70A.100.
(3)(a) In the absence of a corridor designation in the manner prescribed in subsection (2) of this section, the council shall as part of the preapplication process require the preapplicant to negotiate, as provided by rule adopted by the council, for a reasonable time with affected cities, towns, and counties to attempt to reach agreement about a corridor plan. The application for certification shall identify only the corridor agreed to by the applicant and cities, towns, and counties within the proposed corridor pursuant to the preapplication process.
(b) If no corridor plan is agreed to by the applicant and cities, towns, and counties pursuant to (a) of this subsection, the applicant shall propose a recommended corridor and electrical transmission facilities to be included within the proposed corridor.
[ 2007 c 325 § 3.]