(1)(a) Sections 510, 512, 514, 516, 518, 520, 522, and 524, chapter 37, Laws of 2017 3rd sp. sess., sections 9, 13, 17, 22, 24, 30, 32, and 45, chapter 135, Laws of 2017, sections 104, 110, 117, 123, 125, 129, 131, and 150, chapter 114, Laws of 2010, and sections 1, 2, 3, and 5 through 10, chapter 149, Laws of 2003 are contingent upon the siting and commercial operation of a significant semiconductor microchip fabrication facility in the state of Washington by January 1, 2024.
Terms Used In Washington Code 82.32.790
- Contract: A legal written agreement that becomes binding when signed.
- person: may be construed to include the United States, this state, or any state or territory, or any public or private corporation or limited liability company, as well as an individual. See Washington Code 1.16.080
(b) For the purposes of this section:
(i) “Commercial operation” means the same as “commencement of commercial production” as used in RCW 82.08.965.
(ii) “Semiconductor microchip fabrication” means “manufacturing semiconductor microchips” as defined in RCW 82.04.426.
(iii) “Significant” means the combined investment of new buildings and new machinery and equipment in the buildings, at the commencement of commercial production, will be at least one billion dollars.
(2) The sections referenced in subsection (1) of this section take effect the first day of the month in which a contract for the construction of a significant semiconductor fabrication facility is signed, if the contract is signed and received by January 1, 2024, as determined by the director of the department of revenue.
(3)(a) The department of revenue must provide notice of the effective date of the sections referenced in subsection (1) of this section to affected taxpayers, the legislature, and others as deemed appropriate by the department.
(b) If, after making a determination that a contract has been signed and the sections referenced in subsection (1) of this section are effective, the department discovers that commencement of commercial production did not take place within three years of the date the contract was signed, the department must make a determination that chapter 149, Laws of 2003 is no longer effective, and all taxes that would have been otherwise due are deemed deferred taxes and are immediately assessed and payable from any person reporting tax under RCW 82.04.240(2) or claiming an exemption or credit under RCW 82.04.426, 82.04.448, 82.08.965, 82.12.965, 82.08.970, 82.12.970, or 84.36.645. The department is not authorized to make a second determination regarding the effective date of the sections referenced in subsection (1) of this section.
(4)(a) This section expires January 1, 2024, if the contingency in subsection (2) of this section does not occur by January 1, 2024, as determined by the department.
(b) The department must provide written notice of the expiration date of this section and the sections referenced in subsection (1) of this section to affected taxpayers, the legislature, and others as deemed appropriate by the department.
[ 2022 c 56 § 11; 2019 c 449 § 2; 2017 3rd sp.s. c 37 § 526; (2017 3rd sp.s. c 37 § 525 expired January 1, 2018). Prior: 2017 c 323 § 509; 2017 c 135 § 47; prior: 2010 c 114 § 201; 2010 c 106 § 401; 2009 c 461 § 9; 2006 c 300 § 12; 2003 c 149 § 12.]
NOTES:
Effective date—2017 3rd sp.s. c 37 §§ 101-104, 403, 503, 506, 508, 510, 512, 514, 516, 518, 520, 522, 524, 526, 703, 705, 707, and 801-803: See note following RCW 82.04.2404.
Expiration date—2017 3rd sp.s. c 37 §§ 502, 505, 507, 509, 511, 513, 515, 517, 519, 521, 523, and 525: See note following RCW 82.04.2404.
Tax preference performance statement exemption—Automatic expiration date exemption—2017 c 323: See note following RCW 82.04.040.
Effective date—2017 c 135: See note following RCW 82.32.534.