(1) The recipient of a deferral certificate under RCW 82.94.030 must begin meaningful construction on an eligible investment project within two years of receiving a deferral certificate, unless construction was delayed due to circumstances beyond the recipient’s control. Lack of funding is not considered a circumstance beyond the recipient’s control.

Ask a legal question, get an answer ASAP!
Click here to chat with a lawyer about your rights.

(2) If the recipient does not begin meaningful construction on an eligible investment project within two years of receiving a deferral certificate, the deferral certificate issued under RCW 82.94.030 is invalid and taxes deferred under this chapter are due immediately.