707.56(5)

Ask a legal question, get an answer ASAP!
Click here to chat with a lawyer about your rights.

(5) Governmental restrictions, regulations or control.

707.56(9)

(9) Forces not under the control or supervision of the developer.

707.56(8)

(8) Acts of God.

707.56(6)

(6) Inability to obtain any materials or services.

707.56(7)

(7) Fire or other casualties.

707.56(1)

(1) Labor disputes not caused by the developer.

707.56(2)

(2) Riots.

707.56(3)

(3) Civil commotion or insurrection.

707.56

707.56 Developer’s obligation to complete improvements. The developer shall complete all promised improvements as described in the time-share instrument, promotional materials, advertising and the time-share disclosure statements. The developer shall be excused for the period or periods of delay in the completion of any promised improvement if delayed, hindered or prevented from doing so by causes beyond the developer’s control, including any of the following:

707.56(4)

(4) War or warlike operations.