A. If any person or business entity desires to temporarily carry on any function, activity, work or operation in closer proximity to any high voltage overhead line than permitted by this article, the person or business entity responsible for performing the work shall promptly notify the public utility operating the high voltage overhead line. The person or business entity may perform the work only after satisfactorily mutual arrangements, including coordination of work and construction schedules, have been made between the public utility operating the lines and the person or business entity responsible for performing the work. Arrangements may include placement of temporary mechanical barriers to separate and prevent contact between material, equipment or persons and the high voltage overhead lines or temporary deenergization and grounding or temporary relocation or raising of the high voltage overhead lines.

Ask a business law question, get an answer ASAP!
Thousands of highly rated, verified business lawyers.
Click here to chat with a lawyer about your rights.

Terms Used In Arizona Laws 40-360.43

  • business entity: means those parties that contract to perform any function or activity on any land, building, highway or other premises. See Arizona Laws 40-360.41
  • High voltage: means voltage in excess of six hundred volts measured between conductors or between a conductor and the ground. See Arizona Laws 40-360.41
  • including: means not limited to and is not a term of exclusion. See Arizona Laws 1-215
  • Overhead line: means all bare or insulated electrical conductors installed aboveground. See Arizona Laws 40-360.41
  • Person: includes a corporation, company, partnership, firm, association or society, as well as a natural person. See Arizona Laws 1-215
  • Public utility: includes public service corporations, municipally owned systems and districts subject to article XIII, section 7, Constitution of Arizona. See Arizona Laws 40-360.41

B. The person or business entity responsible for performing the work in the vicinity of the high voltage overhead lines shall pay any actual expenses of the public utility operating high voltage overhead lines in providing arrangements for clearances, except in instances where the public utility operating high voltage overhead lines has installed lines within ten feet of an existing fixture or structure after the fixture or structure has been in place at the permanent location. The public utility is not required to provide the arrangements for clearances until an agreement for payment has been made.

C. The public utility shall commence construction for temporary clearances within five working days of an agreement for payment, if required, or from the date of the request of the person responsible for the work. Once initiated, the clearance work will continue without interruption to completion.