A. An agency shall issue a written notice of administrative completeness or deficiencies to an applicant for a license within the administrative completeness review time frame.

Ask a legal question, get an answer ASAP!
Click here to chat with a lawyer about your rights.

Terms Used In Arizona Laws 41-1074

  • Action: includes any matter or proceeding in a court, civil or criminal. See Arizona Laws 1-215
  • Administrative completeness review time frame: means the number of days from agency receipt of an application for a license until an agency determines that the application contains all components required by statute or rule, including all information required to be submitted by other government agencies. See Arizona Laws 41-1072
  • Agency: means any board, commission, department, officer or other administrative unit of this state, including the agency head and one or more members of the agency head or agency employees or other persons directly or indirectly purporting to act on behalf or under the authority of the agency head, whether created under the Constitution of Arizona or by enactment of the legislature. See Arizona Laws 41-1001
  • License: includes the whole or part of any agency permit, certificate, approval, registration, charter or similar form of permission required by law, but does not include a license required solely for revenue purposes. See Arizona Laws 41-1001
  • Overall time frame: means the number of days after receipt of an application for a license during which an agency determines whether to grant or deny a license. See Arizona Laws 41-1072

B. If an agency determines that an application for a license is not administratively complete, the agency shall include a comprehensive list of the specific deficiencies in the written notice provided pursuant to subsection A of this section. If the agency issues a written notice of deficiencies within the administrative completeness time frame, the administrative completeness review time frame and the overall time frame are suspended from the date the notice is issued until the date that the agency receives the missing information from the applicant.

C. If an agency does not issue a written notice of administrative completeness or deficiencies within the administrative completeness review time frame, the application is deemed administratively complete. If an agency issues a timely written notice of deficiencies, an application is not complete until the agency receives all requested information.

D. Except for an application submitted to the department of water resources pursuant to title 45, a determination by an agency that an application is not administratively complete is an appealable agency action, which if timely initiated, entitles the applicant to an adjudication on the merits of the administrative completeness of the application.