Iowa Code 476A.4 – Hearing scheduled — notice
Current as of: 2024 | Check for updates
|
Other versions
1. The proceeding for the issuance of a certificate or an amendment to a certificate shall be treated in the same manner as a contested case pursuant to the provisions of chapter 17A. Upon acceptance of an application by the board, a public hearing shall be scheduled.
Terms Used In Iowa Code 476A.4
- Amendment: A proposal to alter the text of a pending bill or other measure by striking out some of it, by inserting new language, or both. Before an amendment becomes part of the measure, thelegislature must agree to it.
- Board: means the utilities board. See Iowa Code 476A.1
- Certificate: means a certificate of title. See Iowa Code 462A.2
- Certificate: means a certificate of public convenience, use and necessity issued pursuant to section 476A. See Iowa Code 476A.1
- Facility: means any electric power generating plant or a combination of plants at a single site, owned by any person, with a total capacity of twenty-five megawatts of electricity or more and those associated transmission lines connecting the generating plant to either a power transmission system or an interconnected primary transmission system or both. See Iowa Code 476A.1
- following: when used by way of reference to a chapter or other part of a statute mean the next preceding or next following chapter or other part. See Iowa Code 4.1
- week: means seven consecutive days. See Iowa Code 4.1
2. The board shall serve notice of the proceeding on the following:
a. Interested agencies, as determined by the board, and regulatory agencies.
b. County and city zoning authorities from the area in which the proposed site is located.
c. Owners of record of real property located within one thousand linear feet of the proposed site.
3. Notice of the proceeding in the form provided in section 17A.12, subsection 2, shall be published in a newspaper of general circulation in each county in which the proposed site is located once a week for two consecutive weeks with the second publication being at least twenty days prior to the date of the hearing. The board shall be responsible for publication and delivery of notices required by this section.
4. The board shall conduct the hearing, as described in subsection 1, in the county in which the construction of the greater portion of the facility is being proposed.
5. A proceeding for the issuance of a certificate under section 476A.5 may be consolidated with a contested case proceeding for determination of applicable ratemaking principles under section 476.53.