(A) When in the opinion of the owner referred to in section 153.01 of the Revised Code, the work under any contract made under any law of the state is neglected by the contractor or such work is not prosecuted with the diligence and force specified or intended in the contract, such owner may make requisition upon the contractor for such additional specific force or materials to be brought into the work under such contract or to remove improper materials from the grounds as in their judgment the contract and its faithful fulfillment requires.

Ask a legal question, get an answer ASAP!
Click here to chat with a lawyer about your rights.

Terms Used In Ohio Code 153.17

  • Appropriation: The provision of funds, through an annual appropriations act or a permanent law, for federal agencies to make payments out of the Treasury for specified purposes. The formal federal spending process consists of two sequential steps: authorization
  • Contract: A legal written agreement that becomes binding when signed.
  • in writing: includes any representation of words, letters, symbols, or figures; this provision does not affect any law relating to signatures. See Ohio Code 1.59
  • Settlement: Parties to a lawsuit resolve their difference without having a trial. Settlements often involve the payment of compensation by one party in satisfaction of the other party's claims.
  • state: means the state of Ohio. See Ohio Code 1.59

Not less than five days’ notice in writing of such action shall be served upon the contractor or the contractor’s agent in charge of the work. If the contractor fails to comply with such requisition within fifteen days, such owner with the written consent of the Ohio facilities construction commission, may employ upon the work the additional force, or supply the special materials or such part of either as is considered proper, and may remove improper materials from the grounds.

(B) When the original contractor has defaulted on a contract and the surety has declined to take over the project, the owner may contract with one or more takeover contractors to complete work that was not finished because of the default of the original contractor. The owner may enter into a contract with a takeover contractor without competitive bidding or controlling board approval.

When the owner has taken over a project after a default has occurred, any moneys that the owner receives from the surety as a settlement for completion of the project shall be deposited in the original fund from which the capital appropriation for the project was made. The executive director, without controlling board approval, may authorize specified additional uses for the moneys related to completion of the project and may increase the appropriation authority in the appropriation line item used to fund the project by an amount equal to the moneys received from the surety.

Last updated September 14, 2023 at 1:57 PM