(1) A utility facility established under ORS § 215.213 (1)(c)(A) or 215.283 (1)(c)(A) is necessary for public service if the facility must be sited in an exclusive farm use zone in order to provide the service.

Ask a real estate law question, get an answer ASAP!
Thousands of highly rated, verified real estate lawyers.
Specialties include: All Real Estate Law, Landlord and Tenant Law, Foreclosure, Homeowners' Association, Trespassing, Property Law, General Legal and more.
Click here to chat with a lawyer about your rights.

Terms Used In Oregon Statutes 215.275

(2) To demonstrate that a utility facility is necessary, an applicant for approval under ORS § 215.213 (1)(c)(A) or 215.283 (1)(c)(A) must show that reasonable alternatives have been considered and that the facility must be sited in an exclusive farm use zone due to one or more of the following factors:

(a) Technical and engineering feasibility;

(b) The proposed facility is locationally dependent. A utility facility is locationally dependent if it must cross land in one or more areas zoned for exclusive farm use in order to achieve a reasonably direct route or to meet unique geographical needs that cannot be satisfied on other lands;

(c) Lack of available urban and nonresource lands;

(d) Availability of existing rights of way;

(e) Public health and safety; and

(f) Other requirements of state or federal agencies.

(3) Costs associated with any of the factors listed in subsection (2) of this section may be considered, but cost alone may not be the only consideration in determining that a utility facility is necessary for public service. Land costs shall not be included when considering alternative locations for substantially similar utility facilities. The Land Conservation and Development Commission shall determine by rule how land costs may be considered when evaluating the siting of utility facilities that are not substantially similar.

(4) The owner of a utility facility approved under ORS § 215.213 (1)(c)(A) or 215.283 (1)(c)(A) shall be responsible for restoring, as nearly as possible, to its former condition any agricultural land and associated improvements that are damaged or otherwise disturbed by the siting, maintenance, repair or reconstruction of the facility. Nothing in this section shall prevent the owner of the utility facility from requiring a bond or other security from a contractor or otherwise imposing on a contractor the responsibility for restoration.

(5) The governing body of the county or its designee shall impose clear and objective conditions on an application for utility facility siting under ORS § 215.213 (1)(c)(A) or 215.283 (1)(c)(A) to mitigate and minimize the impacts of the proposed facility, if any, on surrounding lands devoted to farm use in order to prevent a significant change in accepted farm practices or a significant increase in the cost of farm practices on the surrounding farmlands.

(6) The provisions of subsections (2) to (5) of this section do not apply to interstate natural gas pipelines and associated facilities authorized by and subject to regulation by the Federal Energy Regulatory Commission. [1999 c.816 § 3; 2009 c.850 § 9; 2013 c.242 § 5]

 

215.275 was added to and made a part of 215.203 to 215.311 by legislative action but was not added to any other series. See Preface to Oregon Revised Statutes for further explanation.