Utah Code > Title 54 > Chapter 25 > Part 2 – Electrical Power Delivery Quality Plan
Current as of: 2024 | Check for updates
|
Other versions
§ 54-25-201 | Electrical power delivery quality plan for a qualified utility |
Terms Used In Utah Code > Title 54 > Chapter 25 > Part 2 - Electrical Power Delivery Quality Plan
- Commission: means the Public Service Commission. See Utah Code 54-2-1
- Electrical power delivery quality: means the suitability of power delivered to customers as measured in comparison to accepted industry standards on voltage and power quality. See Utah Code 54-25-101
- Electrical power delivery quality plan: means a plan submitted to the commission in accordance with the requirements of this chapter. See Utah Code 54-25-101
- Interconnection request: means a request from a utility-scale energy generation system to a qualified utility's transmission line. See Utah Code 54-25-101
- Qualified utility: means the same as that term is defined in Section 54-17-801. See Utah Code 54-25-101