Sec. 16. (a) A review authority to which a construction plan is submitted must make a preliminary determination whether the construction plan is substantially complete before the end of:

(1) the tenth working day after the day on which the construction plan is submitted to the review authority, in the case of a small or very small construction activity site; or

Ask a legal question, get an answer ASAP!
Click here to chat with a lawyer about your rights.

Terms Used In Indiana Code 13-18-27-16

  • construction plan: means a written plan that:

    Indiana Code 13-18-27-3

  • general permit: refers to the general permit issued by the commissioner or the department in accordance with Indiana Code 13-18-27-6
  • large construction activity site: means :

    Indiana Code 13-18-27-7

  • project site owner: means the person required to comply with 327 IAC 15-5, the general permit, or the applicable ordinance of an MS4 community with respect to a construction project. See Indiana Code 13-18-27-9
  • review authority: means either of the following:

    Indiana Code 13-18-27-10

  • small construction activity site: means :

    Indiana Code 13-18-27-12

  • very small construction activity site: means a site at which construction activities result in land disturbance of less than one (1) acre. See Indiana Code 13-18-27-14
(2) the fourteenth working day after the day on which the construction plan is submitted to the review authority, in the case of a large construction activity site.

     (b) If a review authority to which a construction plan is submitted under subsection (a):

(1) makes a preliminary determination that the construction plan is substantially complete; and

(2) notifies the project site owner of its favorable preliminary determination;

before the end of the tenth working day after the day on which the construction plan is submitted to the review authority, in the case of a small or very small construction activity site, or the fourteenth working day after the day on which the construction plan is submitted to the review authority, in the case of a large construction activity site, the project site owner may submit a notice of intent letter including the information required by 327 IAC 15-5-5 or the general permit and, forty-eight (48) hours after submission of the notice of intent letter, may begin the construction project, including the land disturbing activities of the construction project.

     (c) If a review authority to which a construction plan for a small or very small construction activity site or a large construction activity site is submitted under subsection (a) does not notify the project site owner before the end of the tenth working day after the day on which the construction plan is submitted to the review authority, in the case of a small or very small construction activity site, or the fourteenth working day after the day on which the construction plan is submitted to the review authority, in the case of a large construction activity site, of its preliminary determination as to whether the construction plan is substantially complete, the project site owner may submit a notice of intent letter including the information required by 327 IAC 15-5-5 or the general permit and, forty-eight (48) hours after submission of the notice of intent letter, may begin the construction project, including the land disturbing activities of the construction project.

     (d) If a review authority to which a construction plan is submitted under subsection (a) notifies the project site owner before the end of the tenth working day after the day on which the construction plan is submitted to the review authority, in the case of a small or very small construction activity site, or the fourteenth working day after the day on which the construction plan is submitted to the review authority, in the case of a large construction activity site, of its preliminary determination that the construction plan is not substantially complete, the project site owner may not submit a notice of intent letter until the review authority makes a conclusive favorable determination concerning the construction plan under 327 IAC 15-5, the general permit, or the applicable ordinance of the MS4 community.

     (e) If a review authority to which a construction plan is submitted under subsection (a):

(1) makes a preliminary determination that the construction plan is substantially complete; and

(2) makes a conclusive unfavorable determination concerning the construction plan under 327 IAC 15-5, the general permit, or the applicable ordinance of the MS4 community;

the land disturbing activities of the construction project must stop when the review authority notifies the project site owner of the review authority’s conclusive unfavorable determination concerning the construction plan.

As added by P.L.248-2019, SEC.14.